Construction repairs are set to begin on the Veterans Memorial Bridge on South College Street in Smithville within a few days.
“The contractor plans to have the project staked by this Monday, August 28 and will begin work the day after the Labor Day holiday period,” Jennifer Flynn, TDOT Community Relations Officer told WJLE Tuesday.
In June, the Tennessee Department of Transportation awarded the contract to Mid-State Construction Company, Inc. of Livingston for $222,894.68.
The project is scheduled to be completed by October 31, 2017.
TDOT let bids for the project Friday, May 12 and Mid-State was the only bidder. In the February 10 letting, Mid-State bid $238,600.58 but there were no other bids and TDOT rejected it as too high.
The bridge has been closed since Monday, June 27, 2016 when a county landfill truck hit it causing major damage. The bridge was hit again last month by a freightliner car hauler.