Almost two years after construction began, the new Sligo bridge project is progressing at a good pace. In fact, it is ahead of schedule, according to the Tennessee Department of Transportation.
“The project is currently ahead of schedule, so the completion date of June 30, 2016 is definitely very attainable. Work is going well on the project, and they should be doing some bridge deck pours in the near future,” said Jennifer A. Flynn, TDOT Region 2 Community Relations Officer.
The contractor is Massman Construction Company, Incorporated of Kansas City, Missouri. Work began on May 23, 2013. The cost to build the new bridge is $39.2 million