The Tennessee Department of Transportation has several projects planned for DeKalb County in a bid letting set for Friday, March 31.
The projects are as follows:
*The resurfacing (microsurface or thin mix overlay) on U.S. 70 (S.R. 26) from east of S.R. 96 to the Dowelltown City limits. Project Length – 4.780 miles.
*The resurfacing (microsurface or thin mix overlay) on S.R. 96 from the Wilson County line to Center Hill Dam Project Length – 12.660 miles. Total Contract Length – 17.440 miles. Completion Time – On or before 9/30/2017
*The on-call guardrail repair and new guardrail installation on various Interstate and State Routes (several counties included). Completion Time – On or before 6/30/2018
*The crack sealing at various locations on various State Routes. (several counties included)
Project Length – 120.790 miles. Completion Time – On or before 7/31/2017
*The random on-call attenuator repairs on various Interstate and State Routes. (several counties included)
Completion Time – On or before 6/30/2018
*The resurfacing on S.R. 146 from U.S. 70S to the DeKalb County line (Cannon County)
Project Length – 9.510 miles